ORDER GUIDE

Cylinder box MOQ and lead time

A cylinder order starts at 500 pieces, samples in 4 – 6 working days from approved artwork, and runs 10 working days from the later of receipt of the cleared deposit or written sample approval. The floor and the clock are both set by the diameter.

The two numbers, and when the clock starts

Three figures govern a cylinder order. The minimum is 500 pieces as a floor — it moves with the structure. A sample takes 4 – 6 working days from approved artwork. Production takes 10 working days, counted from the later of receipt of the cleared deposit or written sample approval.

The clock does not start at the enquiry and it does not start when the artwork is emailed. It starts when the artwork is approved, because that is the moment the wrap can be printed. A week spent revising a logo is a week added to the end date, and it is the most common cause of a late cylinder order that nobody chose.

Those are working days, and they cover production. Freight is outside them, and so is the sample.

Why a cylinder has a floor at all

The 500 is not a machine minimum. It is the point at which the setup stops being most of the price. A cylinder has three setups: the mandrel or the cutting die, the print plates, and the assembly line — the third being mostly the time it takes to teach a run rather than a tool.

Below that point the buyer is paying for the setup and receiving the boxes almost as a by-product. Above it the setup is spread and the price starts to follow material and minutes. That is why the same box can be quoted at two very different unit prices without either quotation being wrong.

What moves the minimum

The floor is 500, and six decisions move it. They are worth checking before a quantity is chosen, because two of them are settled by the drawing rather than by the order.

DecisionEffect on the minimumWhy
A diameter already tooledNo changeThe mandrel or die exists
A new diameterRisesTooling is made for one size
Shoulder-neck lidRisesThe inner neck is a second formed part
Telescoping lidNeutralOne cylinder, one wall, one printed surface
Wall above 2.5 mmRisesWinding and rim forming take longer per unit
Foil or embossRisesA die per design and an extra pass
Second colourwayFalls, per unitThe tube is shared; only the wrap changes

Where the ten working days go

Production is sequential: material released, tube wound or wall formed, wrap printed, wrap finished, assembled, inspected, packed. No single stage is long. What makes ten days is that they cannot overlap — the wrap cannot be printed before the artwork is approved, and the box cannot be assembled before the wrap is dry.

Two stages absorb most delays. Print restarts if the proof changes. The tube restarts if the wall or the diameter changes, because the mandrel or the die is the wrong size. Both are avoidable at the drawing and neither is avoidable afterwards.

Sampling: 4 – 6 working days, and what the sample settles

A cylinder sample is not a formality. It is the only moment the fit can be held in the hand before 500 pieces exist. It settles the lid clearance, the ovality at the seam, the collar height and the board caliper — four things that cannot be judged from a drawing, and three of which are invisible in a photograph.

The sample runs 4 – 6 working days from approved artwork and costs US$30 – 120 depending on the structure and the finish. The fee buys the physical object and the measurements on it, not just the look.

A new diameter is the long pole

A wound tube is made on a mandrel sized to its diameter. A wrapped cylinder is cut on a die sized to its diameter and height. A size that has not been run before is a tooling item, and tooling happens before the ten days rather than inside them — which is why a new size can add time to a schedule that a repeat size does not.

A change to the wall is the same story. On the 42 mm fragrance box the wall went from 1.5 mm to 2.0 mm after the first sample, because the base bowed when the 118 g bottle was set in and the box was lifted by the wall. The fix was right and it cost one extra sample and about a week, because the tube had to be re-cut.

What adds a week without anyone deciding to

Four things do it, and none of them looks like a delay at the time. Artwork revised after the proof. A wrap that is not in stock in the width the job needs. A carton specified at the end rather than with the box. Three colourways assembled in the wrong order, so the shared tube is wound before the split is agreed.

The fifth is the calendar. Chinese New Year falls between late January and late February, and the factory empties for it. A run approved in December is on the safe side; a run approved in January for a March launch is the one that misses. Nothing on this page changes that, and a schedule that assumes it is not the factory's schedule.

Splitting a run across colourways

A colourway split is cheap at the wrap and expensive at the tube, so the order of operations decides the price. The fragrance box in the case studies ran three colourways that differed only in the wrap and the foil: one tube, one board, three prints. Split after winding and the only extra cost is the print setup; split before and there are three tubes.

This is also the answer to whether two designs can be tested. Yes — if both sit on the same cylinder. If the test is between two diameters, it is two tooling items and two minimums.

The order in time, and what restarts it

StageStarts whenWhat sends it back
Artwork approvedThe proof is signedAny later change to copy or colour
Mandrel or dieThe size is fixedA change to diameter, height or wall
PrintArtwork approved and wrap in stockA revised proof; a paper not in stock
FinishingPrint dryA late decision on foil, emboss or lamination
AssemblyWrap finishedA change to collar, disc or lid lining
Inspection and packingAssembly completeA carton that was never specified

Questions about the minimum and the schedule

What is the minimum order for a cylinder box?

500 pieces as a floor. It moves with the structure: a new diameter, a shoulder-neck lid, a wall above 2.5 mm, a foil die or an insert each push it up, and a second colourway on the same tube pushes the unit price down without moving the floor.

How long does production take?

10 working days from the later of receipt of the cleared deposit or written sample approval. Sampling is 4 – 6 working days before that and freight comes after. Neither the sample nor the freight is inside the ten days.

Can I order fewer than 500?

Ask, and the answer depends on whether the size has been tooled and how simple the structure is. The floor exists because setup is most of the price at that quantity; a job that avoids new tooling has more room than one that needs it.

Does a new diameter add lead time?

Yes. The mandrel or the die is made before production starts, so a new size adds time ahead of the ten days rather than inside them. A diameter that has been run before does not.

Can one run carry three designs?

Yes, if the designs share the tube. The tube is wound once and the wrap is printed three times, so the split costs print setup rather than a second minimum. Three different diameters are three orders.

Board thickness is specified to⁠ ⁠ ISO 534,⁠ ⁠the standard method for the thickness, density and specific volume of paper and board, so a millimetre in a specification means the same thing to both sides.

CUSTOM PROJECT

Start Your Custom Packaging Project

Send your product, quantity and the structures you are weighing up. We will tell you which one fits and what it costs.

Request a Custom Packaging Quote