MANUFACTURING PROCESS

From your brief to a shipped box

Ten stages, in the order they actually happen. Knowing where a project is — and what has to be signed off before the next stage starts — is what keeps a packaging order on schedule.

Ten stages, and where your decisions sit

Custom packaging is not one service with one price tag; it is a sequence of about ten handovers, and at each one something has to be decided before the next can start. Some of those decisions are ours — material behaviour, machine order, how a structure is actually built. The rest are yours, and knowing which is which in advance is most of what separates a project that ships on schedule from one that stalls waiting for an answer.

Read the list below as the order things physically happen on our floor, because it is: nothing gets printed before the structure exists, nothing gets assembled before the printed sheets are finished, and nothing gets packed before it has been checked. Exactly this sequence can be watched happening in real time in the film on our factory page.

01

Project Requirements

Product dimensions, weight, quantity, application, artwork, reference images, materials and finishing requirements are reviewed.

What we are doing in this stage is finding the two or three constraints that will actually decide the structure — usually the heaviest part, the most fragile part, and the quantity — rather than collecting every preference you have. Anything that cannot be resolved here becomes a question later, and later costs more to change than now.

02

Structural Development

The packaging structure is developed around product dimensions, opening method, presentation, material thickness, stability, assembly and shipping considerations.

This is the stage where a box either works or does not. Internal clearances are set here, so this is also the last easy moment to tell us the product dimensions are approximate — a structure built against numbers that later change has to be rebuilt, not adjusted.

03

Material Selection

Materials are selected according to the required structure, appearance and application, including greyboard, specialty papers, coated papers, textured papers and other packaging materials.

Material choice carries cost, weight, print behaviour and how the box feels in the hand, and those four rarely pull in the same direction. We will usually put two options in front of you with the trade-off named explicitly rather than pick quietly on your behalf.

04

Quotation

The project is reviewed according to structure, dimensions, materials, quantity, printing, finishing, accessories and shipping requirements.

Quotes are issued on EXW, FOB, CIF or DDP terms, so that what you are comparing is the landed cost rather than a unit price that hides the freight. If a request sits outside what we can make well, this is where we say so.

05

Prototype & Sampling

Samples can be used to confirm dimensions, structure, materials, artwork, printing, finishing, product fit and overall presentation.

This is the only stage designed to be disagreed with. Put your actual product in the sample, ship it somewhere if that is how it will really travel, and tell us what is wrong — a change made here costs a sample, the same change made after printing costs a run.

06

Artwork & Production Specification

Artwork, materials, dimensions, printing, finishing and assembly specifications are finalized before mass production.

Artwork is checked here for bleed, resolution, colour space and panel alignment against the actual cutting shape. Once this document is signed off it becomes the reference the production floor works to and the inspection in stage nine checks against, so it is worth being certain rather than quick.

07

Mass Production

Production can involve board preparation, printing, mounting, die cutting, folding, box forming, magnetic assembly, finishing and interior assembly.

Everything before this point was preparation; this is where the order physically exists. Work passes between lines rather than staying at one station, which is why tooling is checked against a first-off piece before the run continues.

08

Printing & Finishing

Finishing options may include foil stamping, embossing, debossing, spot UV, lamination and specialty papers.

Every finish is another pass through another machine, and each pass carries its own registration tolerance. Two finishes register cleanly; four take real setup discipline, and we will tell you when a combination is asking for more than the artwork gains from it.

09

Quality Control

Production checks are used to verify important packaging specifications before shipment.

Checking at several points during a run rather than only at the end is what keeps a sixteenth Box one hundred problem from being a sixteen hundred box one. What exactly gets checked, and against which reference, is set out on the quality control page.

10

Packing & Shipment

Finished packaging is packed according to agreed requirements and prepared for shipment.

Carton pack-out, labelling, palletising and moisture protection are decided against how the goods actually travel — sea freight and courier parcels ask for different things, and a factory box that survives a pallet can still lose a corner to a distribution centre.

What each stage hands you, and what it blocks

The same ten stages arranged by ownership. Anything in the "gates" column cannot begin until a decision only you can make has landed, which is the useful thing about this table: it shows where a schedule actually comes from.

StageWhat you receiveWhat you decideWhat it gates
RequirementsA written summary of what we understood you need, including anything we think is missing.Whether our reading of your constraints is correct.Structural development.
StructureA proposed box type with internal clearances and a recommended board build.Whether the opening method and internal layout suit the product.Material selection and a valid quotation.
MaterialsChosen boards, wrap papers and insert material, usually with a cheaper and a better option.Which of the trade-offs you prefer, and confirmation of any sustainability requirement.Final pricing and print method.
QuotationA priced specification with quantity breaks and named Incoterms.Whether to proceed, and at what quantity.Tooling and sampling.
SamplingA physical sample of the real thing, made to the real specification.Written approval, or the changes you want made before anything is run.Artwork release and, later, the production start.
Production specificationA signed-off document covering artwork, dimensions, materials, finishing and assembly.Sign-off. Nothing here is assumed approved because nobody objected.Mass production and any inspection standard.
Production & finishingThe finished run, checked at several points along the way rather than at the end only.Acceptance against the approved sample.Packing.
Packing & shipmentPacked cartons labelled to your requirements, with packing documentation.Shipping terms, consolidation, and who books the collection.The order leaving the factory.

Two owners meet at every line in this table. Projects slip at the handovers, not inside the stages — which is why we will always tell you which decision we are waiting on rather than simply reporting that the order is in progress.

How long the whole sequence takes

Two figures cover almost every project, and both start from a fixed specification rather than from the day you asked: samples take 4 – 6 working days from approved artwork, a separate stage from production. Production takes 10 working days from the later of receipt of the cleared deposit or written sample approval. Transit time is additional.

Where you land within those figures depends on how many printing passes the artwork needs, whether an insert has to be tooled, how much of the assembly is done by hand, and the size of the run. Those are all known at quotation time, so the honest answer to "how long will this take" has already been worked out before you commit to anything.

Sample parcels go out with DHL, UPS or FedEx, typically 3 – 6 days in transit, and production can ship on EXW, FOB, CIF or DDP terms depending on who you want arranging the freight.

Start Your Custom Packaging Project

Send your product dimensions, quantity, artwork, packaging reference or initial concept. METAPACKINK can review the requirements and discuss suitable packaging structures and manufacturing options.

Request a Custom Packaging Quote

Questions about the manufacturing process

How many stages does a project go through?

Ten, in the order they happen: requirements, structural development, materials, artwork and prepress, sampling, approval, production, finishing, quality control and shipment. Each stage has a sign-off before the next begins.

What do you need to start?

The product and its dimensions or a physical sample, the quantity, and any material or finishing preference. Artwork is not needed to start; it is needed before prepress.

When is artwork required?

After the structure and dimensions are confirmed, because the dieline depends on both. Delivering artwork before the structure is fixed usually means redoing it.

Who owns the tooling and the dieline?

The quotation states it. For OEM work the drawing is yours; for ODM work we develop and hold it, and the terms are written into the quotation rather than assumed.

How long is production?

Production runs 10 working days from the later of receipt of the cleared deposit or written sample approval. Sampling itself takes 4 – 6 working days from approved artwork.

The process described here is audited under⁠ ⁠ ISO 9001,⁠ ⁠certificate 04626Q00932R001, issued by Beijing Head International Certification Co., Ltd.

Since 200520+ years manufacturing packaging
two plantsFoshan & Guangzhou
ISO 900104626Q00932R001
AuditedMade-in-China.com · MIC-ASI261850