PLANNING GUIDE

Planning a packaging order around the lead time

A packaging schedule is four clocks, not one. Planning only the production time is how a launch date slips.

The four clocks

Sampling, artwork and prepress, production, and freight. Each has its own trigger. Sampling starts from approved artwork; production starts from the later of receipt of the cleared deposit or written sample approval; freight starts when the order is released.

The triggers matter more than the durations. A production slot cannot start until the sample is approved in writing, so a late approval moves the whole schedule regardless of the factory.

Where schedules slip

Most slips are on the buyer side: artwork arrives late, a sample is approved verbally and the written approval follows a week later, or a colour is changed after plates are made. The factory time is usually the predictable part.

A realistic plan puts the sample approval date first, then works backwards through prepress and artwork, and leaves a buffer for freight. If the buffer is zero, the launch date is a hope.

The artwork clock is the one that slips

Sampling starts from approved artwork, and approved artwork is the step most often late. The usual causes are ordinary: a dieline drawn before the structure was final, text left inside the bleed, fonts not outlined, or a colour specified as a screenshot rather than a reference.

One round of corrections is normal and costs a few days. Two rounds cost a fortnight. The cheapest way to protect a launch date is to send the artwork against the current dieline, with the structure already agreed, and to have one person who can approve it rather than a thread of opinions.

Freight mode changes the promise you can make

Production finishing is not the date a customer experiences; arrival is. Air freight measures in days and costs by weight, sea freight measures in weeks and costs by volume, and a port delay can erase a fortnight that the production schedule delivered exactly.

Terms decide who carries that risk. On a DDP quotation we book the freight, so the arrival date is ours to answer for. On FOB the buyer books it, and the schedule after release belongs to a forwarder. Neither is wrong, but a launch date promised before the mode is chosen is not a plan.

What has to be true before each clock starts

Each stage has one precondition, and the schedule slips when a stage starts without it. Written down, the preconditions are short enough to check in a single email before the order is placed.

The one that matters most is written sample approval. Production runs against the approved sample, so a verbal yes with the written approval following later moves the start date to the day the email arrives, not the day of the phone call.

StageCannot start untilWhat usually blocks it
SampleArtwork approved against the dielineArtwork still in design
ProductionDeposit cleared or approval in writingA verbal approval
FinishingSheets printedA colour change after plates
PackingProduction releasedInsert not confirmed
FreightOrder released, balance settledTerms not agreed at quotation

Which delays move which dates

The four clocks are not one chain. Artwork and prepress run serially with sampling; once production starts, packing and freight booking can be prepared alongside it. A delay only moves the launch date when it sits on the serial path.

That gives a usable test: name the clock the delay belongs to, then ask whether any later stage could have started without it. A colour change after plates sends prepress and sampling back before it touches production. A courier delay moves the approval date but not the artwork already finished. Written approval is the hinge, because it is the one input that gates production and therefore carries every later date with it.

Where the delay landsWhat moves with itWhat does not
Artwork not finalPrepress, sample, production, arrivalFreight booking, once terms are agreed
Written sample approvalProduction, finishing, packing, arrivalArtwork and plates already approved
Colour change after platesPrepress, sample, productionThe agreed structure and dieline
Insert not confirmedPacking and releasePrinted sheets, if the carton is unchanged
Port or customs holdArrival onlyEvery factory-side stage

Stages and triggers

StageTypical timeStarts from
SampleTrade sample lead timeApproved artwork
Artwork and prepressA few daysConfirmed structure
ProductionProduction lead timeLater of receipt of the cleared deposit or written sample approval
FinishingWithin productionPrinted sheets
FreightDepends on lane and modeOrder release

Questions about lead times

How long does a sample take?

Typically 4 – 6 working days from approved artwork, plus courier time. Structural development adds time before that.

How long is production?

Production runs 10 working days from the later of receipt of the cleared deposit or written sample approval.

Can production start before sample approval?

No. The approved sample is the reference the line is measured against, so production waits for it.

What usually delays an order?

Late artwork or a late written approval, not the factory. Both are on the buyer side and both are avoidable.

Should I plan a buffer?

Yes, especially for freight. A schedule with no buffer is a schedule with no room for a port delay.

Delivery terms are read as⁠ ⁠ Incoterms 2020,⁠ ⁠the ICC rules that decide where cost, risk and duty pass from seller to buyer at each named place.

CUSTOM PROJECT

Start Your Custom Packaging Project

Send your product, quantity and the structures you are weighing up. We will tell you which one fits and what it costs.

Request a Custom Packaging Quote
Since 200520+ years manufacturing packaging
two plantsFoshan & Guangzhou
ISO 900104626Q00932R001
AuditedMade-in-China.com · MIC-ASI261850